The MPS for gear housings has a demand time fence at week 3 and a planning time fence at week 8. A sales order arrives for week 2, but ATP is short and a planned receipt exists in week 5. What should the master scheduler do?
Move the week 5 receipt into week 2 because the customer order is firm
Ignore the order until MRP creates component requirements
Increase the forecast in week 2 so the MPS absorbs the order
Protect the frozen zone, quote only available ATP or escalate a formal exception before moving the week 5 receipt.