A project manager wants to load 15,000 people and support-group memberships the night before go-live. The dependency data is still changing daily. Which risk should you flag first?
Changing dependency data can invalidate references and produce routing or access defects after load.
People loads are independent of foundation data and can be safely delayed.
The only risk is that email templates will be duplicated.
Data Management automatically creates all missing companies from person rows.