A BIM clash report shows 1,200 clashes, most involving minor insulation overlaps. The team is overwhelmed and critical mechanical-room conflicts remain unresolved. What should the CM require?
Require the team to close all minor clashes before discussing major ones.
Prioritize clashes by constructability impact, system criticality, location, responsibility, and resolution due date.
Ignore insulation clashes and accept the model once total clashes fall below 1,000.
Move unresolved clashes to the field because trades can coordinate faster onsite.