A PLC-controlled tank level loop oscillates slowly after a PI controller integral time was shortened. The proportional gain was unchanged. Which adjustment is most likely to reduce the slow cycling while preserving proportional action?
Increase the integral time, reducing integral aggressiveness.
Decrease the integral time further.
Remove the process sensor from feedback.
Change the setpoint units from percent to gallons only.