The programme office for a 2025 hospital network merger with clinical, finance, and digital workstreams is training new staff on MSP lifecycle processes. Which description of 'identify the programme' is most accurate?
produce detailed project plans for all supplier work
Treat benefit ownership as complete once the first project has delivered its output.
confirm the mandate, clarify strategic fit, outline vision and high-level benefits, and decide whether to design outcomes
Avoid changing the programme plan because lifecycle processes are intended to preserve the original baseline.