A stakeholder asks the team to guarantee benefits six months ahead before any release. Which response best balances value, risk, team autonomy, and empirical control?
Guarantee the benefits if the sponsor freezes scope.
Refuse to discuss outcomes because agile plans only one sprint at a time.
Estimate benefits using team velocity alone.
Provide a forecast with assumptions and plan to validate benefits through incremental delivery and feedback.