During schedule development/risk planning, A team wants to compare resequencing options before committing to a recovery plan. What is the best PMI-SP action?
Use the deterministic critical path finish because probabilistic dates should not affect baseline decisions.
Average the P50 and P80 dates and use that as the new baseline without change control.
Remove high-uncertainty activities from the network so the simulation output is less volatile.
Use what-if scenario analysis to test alternatives against the current schedule model.