EVP Earned Value Professional Certification Practice Test

110 preguntas disponibles

Gana confianza para EVP Earned Value Professional Certification. Practica los conceptos, comprende las respuestas y refuerza tus conocimientos pregunta a pregunta.

Probar una pregunta
Prueba 5 preguntas gratis
No necesitas cuenta. Una cuenta gratuita incluye 20 preguntas de este examen.
Examen de certificación
Professional Nivel
Tu práctica
110 Preguntas de práctica
1 hora 50 minutos Tiempo de Práctica
Prueba 5 preguntas gratis
No necesitas cuenta. Una cuenta gratuita incluye 20 preguntas de este examen.
El banco 110 Preguntas de práctica verificadas con los objetivos oficiales.
AACE International110 preguntas de práctica
Temario verificadoVerificado con AACE International official objectivesMetadatos verificados 2026-09-02Cómo verificamos

Descripción y detalles del examen

Earned value management certification covering EVM principles, BCWS, BCWP, ACWP, schedule performance, and cost performance for project control professionals. Administered by AACE International. Key domains include Accounting considerations, Analysis and management reports, Organization and Planning, scheduling and budgeting.

Preguntas de Muestra

Elige una respuesta y consulta la explicación para ver cómo funciona la práctica.

EVP Revisions and Data Maintenance

A customer change on the munitions handling line contract is authorized on 12 June 2025, but the CAM wants to wait two reporting cycles before updating the baseline so the team can refine estimates. Work will start next week. What should the EVP recommend?

EVP Revisions and Data Maintenance

Management wants to use MR on the classified data enclave project to cover a realized in-scope risk. The CAM also asks to use the same MR transfer to erase a pre-existing cost variance. Which revision control is correct?

Analysis and management reports

The coastal radar site report shows CV USD -270,000 and SV USD -168,000. The PM asks why the same dollar sign appears on schedule and cost variance even though schedule delay is time-based. What is the best EVP explanation?

Analysis and management reports

A supplier disruption on the traffic management center project makes historical CPI unreliable for remaining work. Actual cost is USD 1.78M, and the CAM's bottom-up ETC for the remaining scope is USD 2.00M. What EAC should the report use?

EVP Perform Budgeting Duties

A risk workshop for the subsea inspection package effort identifies a 30 percent chance of supplier requalification. The work is not in the current contract scope unless the risk occurs. How should the budget be handled in the EV baseline?

Qué temas cubre este examen

01Accounting considerations

02Analysis and management reports

03Organization

04Planning, scheduling and budgeting

05Revisions (change management) and data maintenance

Detalles del Examen EVP

Código del Examen EVP
Proveedor AACE International

Preguntas Frecuentes

¿Cuál es la principal diferencia entre el EVP y otras certificaciones de gestión de proyectos?

¿Cuánta experiencia práctica en EVM se necesita antes de intentar el examen?

¿El examen se centra mucho en cálculos matemáticos?

¿Cuáles son los mejores recursos para la preparación?

¿Cómo beneficia esta certificación a alguien en un rol de contratación gubernamental?