Earned value management certification covering EVM principles, BCWS, BCWP, ACWP, schedule performance, and cost performance for project control professionals. Administered by AACE International. Key domains include Accounting considerations, Analysis and management reports, Organization and Planning, scheduling and budgeting.
नमूना प्रश्न
पूरी परीक्षा कैसी है देखने के लिए कुछ प्रश्न आज़माएं।
137 में से 97 उत्तरों में जाँचने योग्य संदर्भ है।
A customer change on the munitions handling line contract is authorized on 12 June 2025, but the CAM wants to wait two reporting cycles before updating the baseline so the team can refine estimates. Work will start next week. What should the EVP recommend?
Management wants to use MR on the classified data enclave project to cover a realized in-scope risk. The CAM also asks to use the same MR transfer to erase a pre-existing cost variance. Which revision control is correct?
The coastal radar site report shows CV USD -270,000 and SV USD -168,000. The PM asks why the same dollar sign appears on schedule and cost variance even though schedule delay is time-based. What is the best EVP explanation?
A supplier disruption on the traffic management center project makes historical CPI unreliable for remaining work. Actual cost is USD 1.78M, and the CAM's bottom-up ETC for the remaining scope is USD 2.00M. What EAC should the report use?
A risk workshop for the subsea inspection package effort identifies a 30 percent chance of supplier requalification. The work is not in the current contract scope unless the risk occurs. How should the budget be handled in the EV baseline?